Rosedale Station
Easier Access
The TTC’s Easier Access Program is making subway stations accessible. Construction at Rosedale is underway and scheduled to be completed in Q3 2025.
Cross Section Image of Station Elevators
The project will provide a barrier-free path to all levels of the station and include installation of:
- Two elevators
- Improved signage
- CCTV security cameras
Please go to our website for further details on TTC’s Easier Access Program and how we are making transit more accessible.
Project documents
- Pre-construction notice - September 2020
- Pre-construction Community Information - September 2020
- Construction Update - May 2023
Project update
Market conditions have changed since the start of the COVID-19 pandemic concerning the cost of work and the availability of materials which impacted work to make the station accessible. Labour strikes in mid-2022 by several unions also directly impacted the progress of construction work. This included crane and heavy equipment operators, carpenters, and other labourers that are critical to Easier Access work. Project schedules have been reviewed and elevators are scheduled to be in service at Rosedale Station by Q3 2025.
In 2024, the architectural façade enclosed the buildings, allowing for the installation of elevator equipment and key electrical and mechanical systems.
This year, the contractor is completing the final architectural finishes to the elevator lobbies. TTC is also in the final stages of testing and commissioning all installed equipment to ensure a safe and seamless experience for TTC customers.
Caption: Pictures showing the old bus canopy demolition and upgrade, to facilitate construction of the southbound elevator shaft/building.
Caption: Exterior view of the elevator for the southbound platform at Rosedale Station.
Caption: Exterior view of the elevator for the northbound platform at Rosedale Station.
For further information:
Clive Scott
Senior Community Liaison Officer
437-219-5174