What we are doing and why
The TTC is building two new elevators to create a barrier-free path from the street to the subway platform level.
Cross section image of current Line 2 Spadina Station (Bloor) and the new elevators on Spadina Road.
What to expect
The first major phase of work will include shoring and excavation activities for the new elevator shafts, located on the north-west and south-east corners of Spadina Road and Lowther Avenue. Work will be completed in two phases, starting with construction of Elevator 2 (E2) on Lowther Avenue west of Spadina Road and then moving onto Elevator 1 (E1) on east side of Spadina Road.
Traffic and pedestrian details
Traffic on Spadina Road maintained with lane restrictions.
Lowther Avenue west is scheduled to be closed for vehicle access to and from Spadina Road from September 19, 2022, until Q4 2023.
Sidewalk closures / detours will be required.
Work hours
Work will typically take place Monday to Friday between 7 a.m. and 7 p.m. Some work on weekends and overnight may be required.
TTC service